Every year around this time, I get the same call. A company has an ERP or major system go-live set for January 1. The date was picked eighteen months ago because it lines up with the fiscal year. The project team says they're "mostly ready." The CEO wants to know whether to believe them.
This year, I'd point them to the third-quarter earnings calls.
These are well-run companies with experienced integrators. That's my point. Go-live failures rarely come from bad software. They come from a go/no-go decision made on optimism instead of evidence.
Your integrator and project team should recommend. They shouldn't decide. They're too close to it, and they have every reason to say yes.
Before you approve a cutover, ask for evidence, not status colors:
The most valuable thing I can tell a CEO six weeks before go-live is the truth. An independent readiness review takes a couple of weeks. It looks at the evidence, talks to the people doing the work and gives leadership a clear go, conditional go or no-go.
Sometimes the answer is "you're ready." Sometimes it's "move the date four weeks." Four weeks of delay is almost always cheaper than three weeks of not being able to ship.
And if you're a public company, have lenders or are heading toward a sale, keep what you say about the project in line with what the review found. Don't schedule an investor or board update in the middle of hypercare. (I wrote about the warning signs in ERP Implementation Failure: The Warning Signs Every CEO Misses.)
An independent readiness review looks at the evidence behind a planned ERP cutover: end-to-end testing on converted data, cutover rehearsals, data reconciliation, user readiness, the rollback plan and manual workarounds. It usually takes a couple of weeks and gives leadership a clear go, conditional go or no-go recommendation.
The date is often set by the fiscal calendar rather than readiness. Holidays cut into final testing and training, year-end close collides with cutover, and hypercare lands in the first quarter, when problems with orders, invoicing or shipping hit cash flow directly.
Business leadership should decide, based on written criteria and verified evidence. The integrator and project team should make a recommendation, but they are too close to the work, and too invested in the date, to be the final decision makers.
I've led and rescued large ERP and transformation programs for more than 25 years, as a CTO and an executive at NTT Data. I don't sell software or implementation hours, so my only job is to tell you whether you're ready.
If you're facing a January go-live, start with a Program Health Check. If your project is already in trouble, see our project recovery services.
Schedule a Strategy CallAn independent read on whether your program is really ready.
Senior leadership to stabilize a troubled project or go-live.
Senior PM capacity on demand, without permanent headcount.
Lessons from a botched weekend cutover.